A new thermal power plant with a capacity of 550 megawatts in the Sharof Rashidov district of the Jizzakh region has been connected to Uzbekistan's unified electric power system. The station, which started operations on November 20, has the capacity to generate 4.4 billion kilowatt-hours of electricity per year.
According to the Ministry of Energy, the total cost of the project is 500 million dollars. The station was built in cooperation with the Turkish company Cengiz Enerji.
The facility is equipped with modern steam-gas units, including Siemens Energy SGT5-4000F gas turbines. Its efficiency coefficient is higher than 60 percent. According to the ministry's calculations, the station will also make it possible to save up to 500 million cubic meters of natural gas per year.
Construction of the project began in August 2023. By a presidential decree dated November 8, 2023, the main terms for its implementation by attracting direct foreign investments were approved.
According to the agreement, Cenergo is responsible for designing, financing, building, and operating the station. Uzenergosotish has undertaken the obligation to purchase the generated electricity for 25 years.
To finance the project, the company also attracted a long-term loan of 164.25 million euros from DZ BANK and DenizBank AG.
Initially, commissioning the station was planned for 2025. However, the deadlines were revised several times. In February 2026, the Jizzakh regional administration announced that it was planned to fully commission the facility by the end of the year.
The Ministry of Energy expects the new station to increase the country's electricity generation capacities and improve the reliability of supplying consumers with electricity.